    Your Agile team is midway through a sprint when the product owner informs you of a critical compliance change that must be delivered immediately. The team is at full capacity, and adding this would jeopardize sprint commitments. What should you do?

    A. Swap a low-priority task with the compliance item
    B. Ask the team to speed up current work
    C. Cancel the sprint and re-plan with new priority
    D. Reprioritize the backlog for the next sprint

    #28396
    admin
    Keymaster

    Correct Answer is C. Cancel the sprint and re-plan with new priority

    A. Swap a low-priority task with the compliance item
    ❌ Incorrect. Mid-sprint changes break the sprint’s stability and focus.

    B. Ask the team to speed up current work
    ❌ Incorrect. Agile promotes sustainable pace and quality delivery.

    C. Cancel the sprint and re-plan with new priority
    ✅ Correct. Sprint can be canceled if the goal becomes obsolete or invalid.

    D. Reprioritize the backlog for the next sprint
    ❌ Incorrect. Delaying a critical compliance item risks non-compliance.

    Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel

    Pass PMP in the First Attempt : PMP Strategy

    Pass PMI-ACP in the First Attempt : PMI-ACP Strategy

    All PMP/ACP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP/Agile Concepts

    PMP Tips & TricksPMP Tips & Tricks

    Agile Tips & Tricks : Agile Tips & Tricks

    PMP & ACP Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.