  • #28382
    admin
    Keymaster

    Atanu is working as Scrum Master in the Project ABC. Development team completed stories worth 20 story points in sprint 1 and stories worth 24 story points in sprint 2. After sprint 2 they conducted retrospective session which resulted in some improvements and sprint 3, development team decided to do stories worth 31 story points. What velocity will Atanu project for team in sprint 3?

    a. 24
    b. 31
    c. 25
    d. 22

    #28384
    admin
    Keymaster

    Correct answer is B.

    Due to some improvements, team decided to complete 31 story points in the third iteration. Therefore, Scrum Master should respect team’s decision and report team velocity to be 31 for the third iteration.

    Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel

    Pass PMP in the First Attempt : PMP Strategy

    Pass PMI-ACP in the First Attempt : PMI-ACP Strategy

    All PMP/ACP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP/Agile Concepts

    PMP Tips & TricksPMP Tips & Tricks

    Agile Tips & Tricks : Agile Tips & Tricks

    PMP & ACP Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.