    Organization XYZ has been doing its projects through Scrum. After sprint 4, product owner left the company. New product owner joined the project in sprint 5. He requested for few changes in the user stories prioritization. As a scrum master what will you do?

    a. Allow the product owner to make the changes
    b. Guide him that prioritization was done by previous product owner and cannot be changed
    c. Escalate the matter to higher management
    d. Ask the team to continue working on previous priorities.

    #28359
    admin
    Keymaster

    Correct answer is A.

    Product Owner is responsible for the prioritization of the user stories. He ensures that highest value deliverables reach customers as early as possible.

    Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel

    Pass PMP in the First Attempt : PMP Strategy

    Pass PMI-ACP in the First Attempt : PMI-ACP Strategy

    All PMP/ACP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP/Agile Concepts

    PMP Tips & TricksPMP Tips & Tricks

    Agile Tips & Tricks : Agile Tips & Tricks

    PMP & ACP Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.