    Which of the following Crystal methods would be better to follow if the team size is large and the product defect criticality is very high?

    a. Crystal Clear
    b. Crystal Yellow
    c. Crystal Orange
    d. Crystal Magenta

    #6796
    admin
    Keymaster

    Correct answer is D.

    Crystal Magenta is being used when the team size is between 101-200 and defect criticality is related to life.