Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #28322
    admin
    Keymaster

    An agile team was performing very well till the fourth iteration. However, due to some unforeseen situations, it was not able to complete any story in the fifth iteration. How this situation will effect the burndown chart?

    a. Slope of the burndown chart will become negative
    b. Slope of the burndown chart will become zero
    c. Slope of the burndown chart will become positive
    d. Since the situation was unforeseen so fifth iteration would be cancelled

    #28324
    admin
    Keymaster

    Correct answer is B.

    Since zero story points are completed so the burdown graph would become flat. Thus slope would become zero.

    Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel

    Pass PMP in the First Attempt : PMP Strategy

    Pass PMI-ACP in the First Attempt : PMI-ACP Strategy

    All PMP/ACP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP/Agile Concepts

    PMP Tips & TricksPMP Tips & Tricks

    Agile Tips & Tricks : Agile Tips & Tricks

    PMP & ACP Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.