    An Agile team is working on a critical project. Since the project is of high importance, 2 new members joined the team to quickly complete the project. What effect would this situation has on the team velocity in the next iteration?

    a. Team velocity will be increased
    b. Team velocity will remain same
    c. Team velocity will be decreased
    d. Team should re-evaluate its velocity

    #28317
    admin
    Keymaster

    Correct answer is D.

    Team should re-evaluate its velocity. Addition of new members may either increase the velocity due to increased capacity or decrease velocity as training may be required which would cause team members to switch from project work.

    Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel

    Pass PMP in the First Attempt : PMP Strategy

    Pass PMI-ACP in the First Attempt : PMI-ACP Strategy

    All PMP/ACP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP/Agile Concepts

    PMP Tips & TricksPMP Tips & Tricks

    Agile Tips & Tricks : Agile Tips & Tricks

    PMP & ACP Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.