Atanu is working as Scrum Master in the Project ABC. Development team completed stories worth 20 story points in sprint 1 and stories worth 24 story points in sprint 2. After sprint 2 they conducted retrospective session which resulted in some improvements and sprint 3, development team decided to do stories worth 31 story points. What velocity will Atanu project for team in sprint 3?
Due to some improvements, team decided to complete 31 story points in the third iteration. Therefore, team velocity would be 31 for the third iteration.