    Which of the following statements is true?

    a. In Agile, Risk is low at the beginning and then increases and after sometimes it decreases.
    b. In Agile, Risk is high at the beginning and then decreases rapidly.
    c. In Agile, Risk is high at the beginning and then decreases and after sometimes it increases.
    d. In Agile, Risk remains low throughout the project.

    #6594
    admin
    Keymaster

    Correct answer is B.

    In Agile, high risk items are placed at the top of the product backlog which ensures they are developed at the earlier stage. This helps in decreasing risk rapidly as the project progresses.