Correct answer is A.

Deals, Offers and Discount Coupons
As per Scrum, any change request (new requirement, defects) should go to the Product Backlog and then it should be prioritized by the Product Owner. If it critical enough then it can be prioritized accordingly so that it can be developed in the upcoming sprint.