    Team ABC is working on the Product XYZ. It is finished and the team asks few outsiders to try out the product while its members observe how users are interacting with it. What type of testing team is performing?

    a. Usability testing
    b. Exploratory testing
    c. Product testing
    d. Adhoc testing

    #22683
    admin
    Keymaster

    Correct answer is A.

    This is Usability testing. In this type of testing team tries to see how and user interacts with the solution in the realistic situation and tries to uncover problems that might need some changes.

    Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel

    World of Project Management : Mobile App

    Pass PMP in the First Attempt : PMP Strategy

    Pass PMI-ACP in the First Attempt : PMI-ACP Strategy

    All PMP/ACP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP/Agile Concepts

    PMP Tips & TricksPMP Tips & Tricks

    Agile Tips & Tricks : Agile Tips & Tricks

    PMP & ACP Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.