    Organization ABC has been following Agile to execute their projects. Recently they started the complex project and the team wants to know the high level requirements so that they can start the work. How would you proceed?

    a. Refer the Project Roadmap
    b. Refer the Project Charter
    c. Refer the Product Backlog
    d. Refer WBS

    #6559
    admin
    Keymaster

    Correct answer is A.

    Product Roadmap contains high level plan which depicts what all user stories will be implemented in which release.