    An agile team consists of 8 members. All members have got very good relations with each other. In the middle of the Sprint 5, one of the member fell ill and took leave till the end of the Sprint 5. As a Scrum Master, what would you do?

    a. Ask the team to complete all stories as planned in the Sprint Planning meeting.
    b. Reduce the velocity for the Sprint 5 considering only 7 members are available and ask team to finish updated set of user stories.
    c. Reduce the velocity for the Sprint 5 officially but internally ask team members to complete original number of user stories.
    d. Ask the team how much they can complete and communicate the same to other stakeholders.

    #22266
    admin
    Keymaster

    Correct answer is D.

    Since in Agile, Development Team is self-organized and self-directed, therefore, team will decide how many story points they will do considering one of the member went on leave.

    Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel

    World of Project Management : Mobile App

    Pass PMP in the First Attempt : PMP Strategy

    Pass PMI-ACP in the First Attempt : PMI-ACP Strategy

    All PMP/ACP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP/Agile Concepts

    PMP Tips & TricksPMP Tips & Tricks

    Agile Tips & Tricks : Agile Tips & Tricks

    PMP & ACP Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.