    Organization ABC has been following Agile to execute their projects. Recently they started the complex project and the team wants to know high level requirements with approximate plan so that they can start the work. What would you suggest the team to refer to?

    a. Refer the Project Roadmap
    b. Refer the Project Charter
    c. Refer the Product Backlog
    d. Refer WBS

    #22175
    admin
    Keymaster

    Correct answer is A.

    Product Roadmap contains high level plan which roughly depicts what all user stories/epics will be implemented in which release.

    Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel

    World of Project Management : Mobile App

    Pass PMP in the First Attempt : PMP Strategy

    Pass PMI-ACP in the First Attempt : PMI-ACP Strategy

    All PMP/ACP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP/Agile Concepts

    PMP Tips & TricksPMP Tips & Tricks

    Agile Tips & Tricks : Agile Tips & Tricks

    PMP & ACP Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.