    Michael is working in an agile environment. Currently, he is working on 2 different projects and is not able to focus properly on both the projects. In terms of Lean, what kind of waste is this?

    a. Task switching
    b. Partially done work
    c. Motion
    d. Waiting

    #6550
    admin
    Keymaster

    Correct answer is A.

    Since Michael would be switching between two projects, this is an example of task switching waste.