An experienced agile practitioner has been assigned to work on two different projects at a time. In a day, on a rough approximation, he is spending 50% of his time on each of the projects. Which of the following is the type of waste that will most likely occur in such an arrangement?
A. Defects
B. Task switching
C. Partially done work
D. Motion