    During Scrum Retrospective, development team analysed one of the process which they want to improve in the next sprint. They created the plan on how to improve the process efficiency. Where would the team place the work involved in this improvement plan?

    A. Product Backlog
    B. Sprint Backlog
    C. Retrospective Improvement Backlog
    D. Since the development team is self-organizing and self-directing, they just do the work involved in the improvement plan in the next sprint

    #13514
    admin
    Keymaster

    Correct answer is B.

    All improvement goals which the development team planned to take up in upcoming sprints are placed in the sprint backlog.

    Post queries : Queries

    Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel

    World of Project Management : Mobile App

    Pass PMP in the First Attempt : PMP Strategy

    Pass PMI-ACP in the First Attempt : PMI-ACP Strategy

    All PMP/ACP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP/Agile Concepts

    PMP Tips & TricksPMP Tips & Tricks

    Agile Tips & Tricks : Agile Tips & Tricks

    PMP & ACP Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

    #21997
    turkishairlines
    Participant

    hiiii

Viewing 3 posts - 1 through 3 (of 3 total)
  • You must be logged in to reply to this topic.