    An agile team has successfully completed the retrospective process. The facilitator wants to know how the session went. Which of the following technique can help him to gather feedback about retrospective process?

    a. ROTI
    b. ROI
    c. Plus/Delta
    d. SMART goals

    #6526
    admin
    Keymaster

    Correct answer is A.

    ROTI stands for Return on Time Invested. It is used during the closing phase of the retrospective process to know about the effectiveness of the retrospective session.