    Sara, an Agile Coach, was explaining the importance of Burn charts to the team. She explained how burn charts can be useful in tracking down team’s performance. Which of the following statements about burn charts is wrong?

    a. Burndown chart goes down whereas Burnup chart goes up
    b. Burndown chart shows remaining work whereas Burnup chart shows completed work
    c. Burndown chart shows scope changes whereas Burnup chart doesn’t
    d. Burndown chart doesn’t shows scope changes whereas Burnup chart shows it

    #12833
    admin
    Keymaster

    Correct answer is C.

    Burnup charts maps both total work and work completed. In case of scope changes, that work is reflected in the total work.

    Post queries : Queries

    Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel

    World of Project Management : Mobile App

    Pass PMP in the First Attempt : PMP Strategy

    Pass PMI-ACP in the First Attempt : PMI-ACP Strategy

    All PMP/ACP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP/Agile Concepts

    PMP Tips & TricksPMP Tips & Tricks

    Agile Tips & Tricks : Agile Tips & Tricks

    PMP & ACP Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.