    Product owner along with agile team is prioritizing the work items. Which of the following items will be developed first?

    a. Business benefit $3000 and cost of development $1500
    b. Business benefit $3000 and cost of development $1000
    c. Business benefit $5000 and cost of development $4000
    d. Business benefit $5000 and cost of development $6000

    #12607
    admin
    Keymaster

    Correct answer is B.

    In Agile, higher business value item is developed first. Value based analysis helps in deciding true business value after factoring in development cost. In the question, option B has the business value of $3000 – $1000 = $2000, which is highest among all the options.

    Post queries : Queries

    Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel

    World of Project Management : Mobile App

    Pass PMP in the First Attempt : PMP Strategy

    Pass PMI-ACP in the First Attempt : PMI-ACP Strategy

    All PMP/ACP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP/Agile Concepts

    PMP Tips & TricksPMP Tips & Tricks

    Agile Tips & Tricks : Agile Tips & Tricks

    PMP & ACP Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.