    Systems thinking approach categorize projects in terms of their complexity mainly in two areas: project requirements and technological approach. In which of the following scenario, Agile works best?

    a. Requirements and Technology both are clear
    b. Requirements and Technology both are ambiguous
    c. There is some uncertainty in both Requirements and Technology
    d. Requirements are clear but Technology is ambiguous

    #12237
    admin
    Keymaster

    Correct answer is C.

    Agile works best when there is some uncertainty in both requirements and technology. If both are highly uncertain then Agile would not work in that case.

    Post queries : Queries

    Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel

    World of Project Management : Mobile App

    Pass PMP in the First Attempt : PMP Strategy

    Pass PMI-ACP in the First Attempt : PMI-ACP Strategy

    All PMP/ACP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP/Agile Concepts

    PMP Tips & TricksPMP Tips & Tricks

    Agile Tips & Tricks : Agile Tips & Tricks

    PMP & ACP Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.