    An Agile team is working on a critical project. Since the project is of high importance, 2 new members joined the team to quickly complete the project. What effect would this situation has on the team velocity in the next iteration?

    a. Team velocity will be increased
    b. Team velocity will remain same
    c. Team velocity will be decreased
    d. Team should re-evaluate its velocity

    #6482
    admin
    Keymaster

    Correct answer is D.

    Team should re-evaluate its velocity. Addition of new members may either increase the velocity due to increased capacity or decrease velocity as training may be required which would cause team members to switch from project work.

    Pass PMI-ACP in the First Attempt : PMI-ACP Strategy

    All PMI-ACP Question & AnswersQuestion & Answers

    Learn Agile Concepts : Agile Concepts

    Agile Tips & Tricks : Agile Tips & Tricks

    Quiz: 30 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.