Home › Forums › Agile (PMP/ACP/Scrum) Questions and Answers › Agile Question 29 This topic has 1 reply, 1 voice, and was last updated 4 years, 12 months ago by admin. Viewing 2 posts - 1 through 2 (of 2 total) Author Posts June 11, 2020 at 8:26 AM #6313 adminKeymaster Mary was assigned to complete a feature in six days. Not only she completed the assigned feature but added few extra features from her side. These extra features are known as: a. Gold Plating b. Scope Creep c. Value adding features d. Silver Plating June 11, 2020 at 8:28 AM #6315 adminKeymaster Correct answer is A. Gold plating means adding more features to please the customer which was not agreed upon in the scope or product backlog. Pass PMI-ACP in the First Attempt : PMI-ACP Strategy All PMI-ACP Question & Answers: Question & Answers Learn Agile Concepts : Agile Concepts Agile Tips & Tricks : Agile Tips & Tricks Quiz: 20 Questions Challenge Author Posts Viewing 2 posts - 1 through 2 (of 2 total) You must be logged in to reply to this topic. Log In Username: Password: Keep me signed in Log In