    Mary was assigned to complete a feature in six days. Not only she completed the assigned feature but added few extra features from her side. These extra features are known as:

    a. Gold Plating
    b. Scope Creep
    c. Value adding features
    d. Silver Plating

    #6315
    admin
    Keymaster

    Correct answer is A.

    Gold plating means adding more features to please the customer which was not agreed upon in the scope or product backlog.