    Team A is averaging 50 storypoints per three weeks iteration. 200 points worth of functionality is left. How many weeks would be required to complete the development work?

    A. 0.25
    B. 3
    C. 4
    D. 12

    #6295
    admin
    Keymaster

    Correct answer is D.

    Number of iterations required = 200 / 50 = 4
    Number of weeks required = number of iterations * iteration duration = 4*3 = 12