Home › Forums › Agile (PMP/ACP/Scrum) Questions and Answers › Agile Question 28 This topic has 1 reply, 1 voice, and was last updated 5 years ago by admin. Viewing 2 posts - 1 through 2 (of 2 total) Author Posts June 1, 2020 at 11:33 AM #6294 adminKeymaster Team A is averaging 50 storypoints per three weeks iteration. 200 points worth of functionality is left. How many weeks would be required to complete the development work? A. 0.25 B. 3 C. 4 D. 12 June 1, 2020 at 11:35 AM #6295 adminKeymaster Correct answer is D. Number of iterations required = 200 / 50 = 4 Number of weeks required = number of iterations * iteration duration = 4*3 = 12 Pass PMI-ACP in the First Attempt : PMI-ACP Strategy All PMI-ACP Question & Answers: Question & Answers Learn Agile Concepts : Agile Concepts Agile Tips & Tricks : Agile Tips & Tricks Quiz: 20 Questions Challenge Author Posts Viewing 2 posts - 1 through 2 (of 2 total) You must be logged in to reply to this topic. Log In Username: Password: Keep me signed in Log In