Home › Forums › Agile (PMP/ACP/Scrum) Questions and Answers › Agile Question 27 This topic has 1 reply, 1 voice, and was last updated 5 years ago by admin. Viewing 2 posts - 1 through 2 (of 2 total) Author Posts May 23, 2020 at 2:57 PM #6286 adminKeymaster Which of the following techniques make sure our storypoint unit remains consistent for all our estimates over the duration of the project? A. Affinity Estimating B. T-Shirt Size estimating C. Planning Poker D. None of these May 23, 2020 at 3:03 PM #6290 adminKeymaster Correct answer is A. Affinity Estimating ensures that our storypoint unit remains consistent for all our estimates over the duration of the project. Pass PMI-ACP in the First Attempt : PMI-ACP Strategy All PMI-ACP Question & Answers: Question & Answers Learn Agile Concepts : Agile Concepts Agile Tips & Tricks : Agile Tips & Tricks Quiz: 20 Questions Challenge Author Posts Viewing 2 posts - 1 through 2 (of 2 total) You must be logged in to reply to this topic. Log In Username: Password: Keep me signed in Log In