Agile Question 23

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #6079
    admin
    Keymaster

    CEO of the company is very much interested in the breakthrough Project ABC. He directly asks development team for some changes. How should Scrum Master best responds to this request?

    A. Scrum Master discuss with Product Owner how can this request be redirected properly.
    B. Scrum Master himself responds to this request to protect team from outside disruptions.
    C. Since the request came from CEO, Scrum Master asks development team to develop changes immediately.
    D. Scrum Master asks development team to appoint emergent leader who can respond to such requests.

    #6081
    admin
    Keymaster

    Correct answer is A.

    In Scrum, it is the responsibility of the Product Owner to maintain and refine backlog. If any request comes, Product Owner should add it into the backlog and then priortize it so that it can be taken for development.

    Pass PMI-ACP in the First Attempt : PMI-ACP Strategy

    All PMI-ACP Question & AnswersQuestion & Answers

    Learn Agile Concepts : Agile Concepts

    Agile Tips & Tricks : Agile Tips & Tricks

    Quiz: 20 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.