Home › Forums › Agile (PMP/ACP/Scrum) Questions and Answers › Agile Question 22 This topic has 1 reply, 1 voice, and was last updated 5 years, 1 month ago by admin. Viewing 2 posts - 1 through 2 (of 2 total) Author Posts May 4, 2020 at 2:47 PM #6075 adminKeymaster In the Burndown chart, line is 50 points above the projected line. What is the status of the project ? A. Behind schedule B. Ahead of schdule C. On time D. Data is insufficient to share schedule status May 4, 2020 at 2:55 PM #6077 adminKeymaster Correct answer is A. In the Burndown graph, line shows how much work is pending. Since the actual progress line is above the projected line, therefore, it means more work is pending as per planned schedule. Pass PMI-ACP in the First Attempt : PMI-ACP Strategy All PMI-ACP Question & Answers: Question & Answers Learn Agile Concepts : Agile Concepts Agile Tips & Tricks : Agile Tips & Tricks Quiz: 20 Questions Challenge Author Posts Viewing 2 posts - 1 through 2 (of 2 total) You must be logged in to reply to this topic. Log In Username: Password: Keep me signed in Log In