    You are a project manager on a team building network firmware for embedded system. You have called a meeting to give a demo of the latest version of code the team has been working on for a control panel interface to a very technical group of business users and customers. This is the fifth time that you have called a meeting to do a demo like this. And for the fifth time, the user and customer asked for a specific changes. The team will now go back and work on a sixth version, and you will repeat the process again. Which of the following BEST describe this situation?

    A. The team doesn’t understand the requirements
    B. The users and customers doesn’t know what they want
    C. The project need better change control and requirements management practices
    D. The team is delivering value early and continuously

    #5498
    admin
    Keymaster

    Correct answer is D.

    Idea behind delivering early is to get feedback so the team will go back & do the required changes.

    Learn Agile Concepts : Agile Concepts