    What is the process cycle efficiency of a 2-hour meeting if it took you 2 minutes to schedule the meeting in the online calendar tool and 8 minutes to write the agenda and e-mail it to participants?

    A) 90%
    B) 8%
    C) 92%
    D) 96%

    #5633
    admin
    Keymaster

    Correct answer is C.

    Value Add Time = 2 hours = 120 mins
    Non-Value Add Time = 2 + 8 = 10 mins
    Total Cycle Time = 120 + 10 = 130 mins

    Process Efficiency = 120 / 130 = 92%