Correct answer is C.
No. of iterations required to complete the project = 500/25 = 20
No. of weeks required to complete the project = 20*3 = 60 weeks
World of Project Management : Mobile App
Jobs : PM Jobs
Pass PMI-ACP in the First Attempt : PMI-ACP Strategy
All PMI-ACP Question & Answers: Question & Answers
Learn Agile Concepts : Agile Concepts
Agile Tips & Tricks : Agile Tips & Tricks
Quiz:
20 Questions Challenge 50 Questions Challenge
Study Groups: Facebook Whatsapp Telegram