Correct answer is C.
Earlier process efficiency = Value added time / Total Time = 18 / (18 + 18) = 50 %
Now process efficiency = Value added time / Total Time = 18 / (18 + 9) = 67 %
Imrpovement in Process Efficiency = 67% – 50% = 17%
World of Project Management : Mobile App
Jobs : PM Jobs
Pass PMI-ACP in the First Attempt : PMI-ACP Strategy
All PMI-ACP Question & Answers: Question & Answers
Learn Agile Concepts : Agile Concepts
Agile Tips & Tricks : Agile Tips & Tricks
Quiz:
20 Questions Challenge 50 Questions Challenge
Study Groups: Facebook Whatsapp Telegram