    An agile team wanted to improve its process. They used value stream map to check value adding and non-value adding activities. Earlier Value added time was 18 minutes and non-value added time was 18 minutes. After analysing scope of improvement, value added time was 18 minutes and non-value added time was 9 minutes. By what percentage process efficiency got increased?

    a. 50%
    b. 67%
    c. 17%
    d. 57%

    #9291
    admin
    Keymaster

    Correct answer is C.

    Earlier process efficiency = Value added time / Total Time = 18 / (18 + 18) = 50 %

    Now process efficiency = Value added time / Total Time = 18 / (18 + 9) = 67 %

    Imrpovement in Process Efficiency = 67% – 50% = 17%

    World of Project Management : Mobile App

    Jobs : PM Jobs

    Pass PMI-ACP in the First Attempt : PMI-ACP Strategy

    All PMI-ACP Question & Answers: Question & Answers

    Learn Agile Concepts : Agile Concepts

    Agile Tips & Tricks : Agile Tips & Tricks

    Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.