Team ABC adopted Agile to execute the project. Velocity for the first sprint was 18, second sprint was 12, third sprint was 20, fourth sprint was 22, fifth sprint was 22, sixth sprint was 24. What can we deduce from this data regarding team formation stages after sprint 6?
a. The team is in the formation stage
B. The team is in the storming stage
C. The team is in the norming stage
D. The team is in the performing stage
Since the velocity has increased from initial sprints and is now stable, therefore, the team has moved from the storming stage to the performing stage.