An Agile team is managing its work in progress on a Kanban board. After few weeks, WIP limits reached and the team cannot take more work to do from the “Ready” state. What should the team do first?
a. Discuss what to be done to move work from WIP state to Done state
b. Discuss how can we increase the WIP limit
c. Discuss who is not working properly in the team
d. Discuss to incorporate method other than Kanban to track progress
When the WIP limits are reached, the team cannot pull work from the left column. The team should discuss how as a team they can move work from WIP column to the done column.