    During gathering data in the sprint retrospective meeting, team members are involved in the session to know where in the last iteration the team energy was high and where it was low. Which facilitation technique the team is using in this scenario?

    a. Mad, Sad, Glad
    b. Satisfaction Histogram
    c. Color Code Dots
    d. Timeline

    #9129
    admin
    Keymaster

    Correct answer is C.

    In the Color Code Dots facilitation technique, the team members identify where their energy was high and low during the course of the iteration.

    World of Project Management : Mobile App

    Jobs : PM Jobs

    Pass PMI-ACP in the First Attempt : PMI-ACP Strategy

    All PMI-ACP Question & AnswersQuestion & Answers

    Learn Agile Concepts : Agile Concepts

    Agile Tips & Tricks : Agile Tips & Tricks

    Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.