Agile Question 111

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #9071
    admin
    Keymaster

    Team is following Sprint to execute the ongoing project. Team meets during the Sprint planning and decided what they will be executing during the Sprint. One of team member asked Sara, Scrum Master, about the reasons in which Sprint can be cancelled. In which of the following options, sprint can be cancelled?

    a. When the Scrum Master says sprint can be cancelled.
    b. When there is major change in the development team.
    c. When the Sprint Goal becomes obsolete
    d. Sprint cannot be cancelled in any situation

    #9073
    admin
    Keymaster

    Correct answer is C.

    When the Sprint goal for which the sprint was undertaken becomes obsolete then the Sprint can be cancelled.

    World of Project Management : Mobile App

    Pass PMI-ACP in the First Attempt : PMI-ACP Strategy

    All PMI-ACP Question & AnswersQuestion & Answers

    Learn Agile Concepts : Agile Concepts

    Agile Tips & Tricks : Agile Tips & Tricks

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.