    Lara, Programmer, was supposed to work on the user story 1, which, is estimated to be at 5 ideal days. Due to some illness, Lara had to take sudden leaves. User Story 1 was newly assigned to Maria, who was working as Senior Programmer. What effect will be on the ideal days estimation of the user story?

    a. Since Maria is Senior Programmer as compared to Lara so the ideal days estimation will be decreased.
    b. Since User Story 1 was suddenly assigned to Maria so the ideal days estimation will be increased.
    c. Ideal days estimation will remain the same.
    d. Cannot tell about ideal days estimation with the given information.

    #8994
    admin
    Keymaster

    Correct answer is C.

    Ideal days estimation is the estimation without any interrupts in between. It remains same irrespective of who is working upon the user story.

    World of Project Management : Mobile App

    Pass PMI-ACP in the First Attempt : PMI-ACP Strategy

    All PMI-ACP Question & AnswersQuestion & Answers

    Learn Agile Concepts : Agile Concepts

    Agile Tips & Tricks : Agile Tips & Tricks

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

    Study Groups: Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.