Lara, Programmer, was supposed to work on the user story 1, which, is estimated to be at 5 ideal days. Due to some illness, Lara had to take sudden leaves. User Story 1 was newly assigned to Maria, who was working as Senior Programmer. What effect will be on the ideal days estimation of the user story?
a. Since Maria is Senior Programmer as compared to Lara so the ideal days estimation will be decreased.
b. Since User Story 1 was suddenly assigned to Maria so the ideal days estimation will be increased.
c. Ideal days estimation will remain the same.
d. Cannot tell about ideal days estimation with the given information.