    In the retrospective meeting, team discussed few measures to reduce the build time from 10 minutes to 5 minutes. They found that a particular module takes more time and decided to refactor it to improve build time. Team had done such improvements in the past. When the team shared this with Product Owner, product owner asked to implement it in future iterations. What is the problem with this goal?

    a. It is not specific
    b. It is not measurable
    c. It is not attainable
    d. It is not timely

    #8968
    admin
    Keymaster

    Correct answer is D.

    There is no specified time within which the target is to be achieved.

    World of Project Management : Mobile App

    Pass PMI-ACP in the First Attempt : PMI-ACP Strategy

    All PMI-ACP Question & AnswersQuestion & Answers

    Learn Agile Concepts : Agile Concepts

    Agile Tips & Tricks : Agile Tips & Tricks

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

    Study Groups: Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.