    You are a Scrum Master of a team that is consistently producing value and meeting their commitments. Your project sponsor approaches you to assist another team struggle in delivering the product increment at the end of every Sprint. How would you respond to such a request? Select the most appropriate response from the following:

    A) Educate your sponsor that helping other teams in the organization is not part of your role.
    B) Partner with the product owner and Scrum Master of another team, assess their current maturity, make suggestions and offer help based on your findings
    C) Talk team members individually and find out reasons why previous Scrum Master failed in his/her role, submit the report to your sponsor
    D) Ask your project sponsor to talk to your manager and wait for official approval before you move to another team

    #5539
    admin
    Keymaster

    Correct answer is B.
    Option A is incorrect because helping the organization to adopt Agile is one of the Scrum Master responsibilities.
    Option C is wrong; meeting individually with each team member is not a problem but focusing only on the Scrum Master may not be the right approach.
    Option D is incorrect as Sponsor asks for the help but does not ask to move to a new team permanently.