    All of the following are examples of Command and Control management approach except:

    a. Sharing Gantt chart on the team’s wall
    b. Putting suggestion box to invite ideas
    c. Prepare the WBS
    d. Divide and assign the tasks to team members

    #7107
    admin
    Keymaster

    Correct answer is B.

    Command and control approach excludes team members from suggestions and planning processes. Putting suggestion to invite ideas of team members involve their participation which is more like servant leadership approach.

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area based Quiz:
    20 Questions Challenge
    50 Questions Challenge

    PMP Agile based Quiz:
    20 Questions Challenge
    50 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.