    During retrospective, team list down goal for the upcoming sprint to improve their performance. They goal is to reduce the time taken for the release process within the next sprint. Few team members already did it while working in another projects. What is the main problem with this improvement goal?

    a. Not time bound
    b. Not attainable
    c. Not specific
    d. Not measurable

    #7100
    admin
    Keymaster

    Correct answer is D.

    Any type of goal should be SMART (Specific, Measurable, Attainable, Relevant, Timely). In this case, improvement goal is time bound (need to implement in next sprint), attainable (few team members already did it in other projects), and specific (reduce the time taken for release process). This is not measurable because it is not mentioned by how much time release process should be reduced.

    Pass PMI-ACP in the First Attempt : PMI-ACP Strategy

    All PMI-ACP Question & AnswersQuestion & Answers

    Learn Agile Concepts : Agile Concepts

    Agile Tips & Tricks : Agile Tips & Tricks

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.