    Lara, Project Manager, is in the process of risk identification. She identified that there are some conflicts in the team as to how to execute certain part of the deliverable. What she would do to mitigate the risk?

    a) Outsource that piece of work
    b) Introduce training on conflict resolution techniques
    c) Insure that piece of work
    d) Remove that piece of work

    #7091
    admin
    Keymaster

    Correct answer is B.

    Best way to mitigate the risk is to provide training on conflict resolution techniques. This will equip team to resolve their conflicts and work together. Outsourcing, Insuring amd Removing are more like transferring and avoiding risks.

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area based Quiz:
    20 Questions Challenge
    50 Questions Challenge

    PMP Agile based Quiz:
    20 Questions Challenge
    50 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.