    After the completion of the sprint 3, Maria (Product Owner) released the product in the market. Maria received query from the business team that there are few defects in the product. What would be the best way to handle this scenario?

    a. Maria should add those defects in the form of user stories in the product backlog and prioritize it.
    b. As the product is already in the market, Maria should add those defects in the form of user stories in the product backlog and fix them immediately in the next sprint.
    c. Maria should ask development team to fix defects and release the product immediately without waiting for product backlog refinement.
    d. Maria should add extra resources in the testing to ensure defects should not escape next time.

    #7080
    admin
    Keymaster

    Correct answer is A.

    As per Scrum, any change request (new requirement, defects) should go to the Product Backlog and then it should be prioritized by the Product Owner. If it critical enough then it can be prioritized accordingly so that it can be developed in the upcoming sprint.

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    PMP Knowledge Area based Quiz:
    20 Questions Challenge
    50 Questions Challenge

    PMP Agile based Quiz:
    20 Questions Challenge
    50 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.