Home › Forums › PMP Questions and Answers Discussion › PMP Question 98 This topic has 1 reply, 1 voice, and was last updated 4 years, 10 months ago by admin. Viewing 2 posts - 1 through 2 (of 2 total) Author Posts July 4, 2020 at 3:22 AM #6840 adminKeymaster An agile team wants to do some experiment to learn about newp approach What technique they should use? a. Iteration 0 b. Iteration H c. Sprint d. Spike July 4, 2020 at 3:26 AM #6841 adminKeymaster Correct answer is D. Spikes are of short duration cycles which developmemt team use to learn new approach and gain knowledge about something. Pass PMP in the First Attempt : PMP Strategy All PMP Question & Answers: Question & Answers Revise PMP Concepts: PMP Concepts PMP Tips & Tricks: PMP Tips & Tricks Quiz: 20 Questions Challenge 50 Questions Challenge PMP Agile based Quiz: 30 Questions Challenge Author Posts Viewing 2 posts - 1 through 2 (of 2 total) You must be logged in to reply to this topic. Log In Username: Password: Keep me signed in Log In