    The development team gathered to break user stories into tasks. The team is involved in which ceremony?

    A. Release Planning
    B. Iteration Planning
    C. Daily Stand-up
    D. None of the above

    #6210
    admin
    Keymaster

    Correct answer is B.

    In the iteration planning, team discuss user stories and breaks them into tasks at the last responsible moment. Tasks are the smallest chunks of work required to build the story.