  • #5981
    admin
    Keymaster

    All of the following statements about Work Breakdown Structure are TRUE except?

    a) Project manager creates it
    b) WBS prevents work from slippage through the cracks
    c) WBS provides a basis for estimating the project
    d) WBS helps to organize the work

    #5982
    admin
    Keymaster

    The correct answer is A.

    Whole team helps in preparing the WBS. This has got additional benefit that it ensures team buy-in.