    Your team is new to agile and is stumped by how to estimate their velocity for planning the first iteration. You advise them to:

    A. Use the velocity established by other agile teams in the organization
    B. Estimate based on their historical data from previous projects
    C. Make a “barely sufficient” guess to use as a starting point
    D. Determine how much of the backlog they will be able to complete

    #5890
    admin
    Keymaster

    Correct answer is D.

    Agile teams estimate their velocity for the first iteration not by guessing, but by deciding how many of the top-priority items in the backlog they can commit to completing in the first iteration. The total story points for these stories becomes their starting velocity estimate. Velocity from previous projects and other teams isn’t relevant, since velocity is unique to each team and project.

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

    PMP Agile based Quiz:
    20 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.