    What would be project manager’s role during Storming phase of the team development?

    a) Directing
    b) Coaching
    c) Supporting
    d) Delegating

    #5591
    admin
    Keymaster

    Correct answer is b.

    In the storming phase, project manager’s role is more of coaching style. It should be high directive and high supportive.