    You have just been assigned as a project manager for a large manufacturing project, this one year project is about halfway done. It involves 5 different sellers and 20 members of your company on the project team. You want to quickly review where the project now stands. Which of the following reports would be MOST helpful in finding such information?

    a) Work status
    b) Progress
    c) Forecast
    d) Communications

    #5586
    admin
    Keymaster

    The correct answer is B.

    Progress report, which summarizes project status, is most helpful in viewing the status quickly.The status report is detailed one and cannot be checked quickly.