    You are in the middle of executing a major modification to an existing product when you learn that the resources promised at the beginning of the project are not available. The BEST thing to do is to?

    a) Show how the resources were originally promised to your project
    b) Replan the project without the resources
    c) Explain the impact if the promised resources are not made available
    d) Crash the project

    #5476
    admin
    Keymaster

    The correct answer is C.

    Project Manager should evaluate and share the impact of not having those resources and try to convince stakeholders of having those resources on the project.