    Project is being executed in the Agile methodology. John has recently joined the team and wondering whom should he approach to know about his role and responsibilities in the project. John approached Susie, scrum master. What does Susie do?

    a) Susie herself shares the responsibilities of John
    b) Susie tells John to contact his project team members
    c) Susie checks with Product owner about what work to be given to John
    d) Susie checks with Project Sponsor about what work to be given to John

    #5414
    admin
    Keymaster

    Correct answer is b.

    In Agile, Development Team is self-directing and self-organizing.