Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #5117
    admin
    Keymaster

    After the kick of meetings, two team members engage in a casual conversation about the project objectives and deliverables. It is clear they heard different messages during the meeting. One team member is so adamant that the other team member gives up the argument. In talking to the project manager, the second team member confirms that the first project team member is mistaken. At this point, what is the BEST course of action?

    a) The second team member should send the other team member an email describing what he discovered.
    b) At the next project meeting, the team member should ask the mistaken team member to describe his interpretation so that project manager can include everyone on the same page.
    c) The project manager should send out an email to the team restating the project objectives and deliverables.
    d) Call project meeting in which the project manager should spend time reviewing the
    documented project scope statement for the purpose of identifying this and other false
    assumptions.

    #5119
    admin
    Keymaster

    The correct answer is D.

    Choice D treats all team members with respect and preserves an individual’s integrity while identifying gaps in the project scope statement. It also allows the project manager to interpret body language of those who misunderstood.

    Pass PMP in the First Attempt : PMP Strategy

    Revise PMP ConceptsPMP Concepts

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.